Naples Beach Is Getting New Sand Before Christmas. Getting to It North of Central Avenue Is Another Story.

November 12, 2026

Dump trucks loaded with sand from an Immokalee mine are rolling onto Naples Beach six days a week. Their stretch runs 3.5 miles, from Doctors Pass down to just south of 21st Avenue South. Walk the beach from Lowdermilk Park toward the pier and the new sand looks the same along the whole shoreline. The way down to it does not. From 4th Avenue North to Central Avenue, every beach end is still fenced, and so is 8th Avenue North.

The fences have nothing to do with the sand trucks. Two projects are working the same shoreline this season on very different schedules. The sand should be in place by the holidays. The north beach ends wait on a pair of pump stations, and those won't be fully running until 2027.

The Sand Is on a Holiday Deadline

Collier County hired Earth Tech Enterprises, a Fort Myers company, to haul and spread more than 208,000 tons of beach-quality sand from Stewart Mining in Immokalee. The whole project costs about $8 million. Roughly $5 million of that is the Earth Tech contract and $2.4 million is the sand itself. It's paid for with Tourist Development taxes, the bed tax collected from people staying in Collier County lodging.

WINK News reported that this stretch lost a lot of sand during Hurricanes Helene and Milton. It also reported that the job will take about 9,450 truck trips on two set routes, which lead to the north and south beach accesses. One beachgoer told the station that the beach had become "a harder sand to walk on now than I'm used to."

The county's schedule, for anyone planning beach time around it:

  • Work hours: Monday through Saturday, 7 a.m. to 7 p.m. Sundays are quiet.
  • Thanksgiving break: crews stop from November 26 through November 29.
  • Finish: the county expects the contractor to wrap up before the end of 2026. WINK put the target at Christmas.
  • On the sand: the beach stays open. Small areas are fenced off where crews are working, and spotters watch the trucks as they move along the beach.

WINK reported that the fenced work zones open back up as each section is finished. So the closure moves along the shore with the crews. It doesn't hold one spot all winter.

One Truck Entrance at a Time

The county's bid documents name two construction entrances for the trucks, the 3rd Avenue North and 17th Avenue South beach ends. In August, a bidder asked whether crews could use both at once and work in from each end to finish faster. The county said no. Its answer, posted on the procurement Q&A, reads: "Only one designated beach access point will be allowed at one time during construction."

That shapes the whole season. The truck traffic won't be split evenly between the two ends of the beach. It will build up around whichever entrance is active. On the city's status page, 17th Avenue South is listed as open to the public. 3rd Avenue North is listed as closed, for a different project entirely.

Why the North Beach Ends Are Still Fenced

That other project is the city's Naples Beach Stormwater Outfall Project. At the direction of the Florida Department of Environmental Protection, it is removing all eight city stormwater pipes that now empty onto the beach and into the Gulf. It also raises the drainage system's capacity from a 5-year storm to a 25-year storm. The work runs along the Gulf Shore Boulevard right-of-way from Oleander Drive to just south of 2nd Avenue South, and the price is $86 million. The State of Florida is covering $40 million of it through legislative appropriations.

The pipes can't come out first. Gulfshore Business reported that the pipes will be removed from the city's beaches once the new system is fully operational. Here is where each step stands on the project's progress page:

  1. Offshore outfalls: done. All 3,200 linear feet of 36-inch pipe running out into the Gulf is in, and the offshore diffusers for both pump stations went in during August 2026.
  2. South Pump Station: testing. It's about 95 percent complete. Startup began in September, and testing continues through November 2026. The south basin is now connected from Alligator Lake to the station.
  3. Gulf Shore Boulevard North: final phase. Drainage and watermain work from 4th Avenue North to 1st Avenue North is substantially complete. The last stretch, from 1st Avenue North to 2nd Avenue South, is expected to be substantially complete by the end of 2026.
  4. North Pump Station: not yet wired. It's about 80 percent complete. Electrical and controls work is scheduled for December 2026 through January 2027, with commissioning in early 2027.
  5. Final completion: 2027. The contract deadline is June 4, 2027. Contractor Kiewit estimates May 2027 and says it may finish earlier.

The project page once said the 8th and 3rd Avenue North beach ends would be closed "until summer 2026." That date has passed, and the city's status table still lists both as closed. Many parts of the work are running ahead of the original schedule. The 3rd Street improvements finished three months early, and the South Pump Station is about three months ahead. Even so, the north pump station's wiring runs into the new year, so the beach ends tied to this project go with it.

Which Beach End to Use This Season

The city's beach access status page is the one to check before you head out. Here's how it lays out the shoreline from north to south as it stands now:

Stretch Beach ends listed open Beach ends listed closed What's behind it
North of 8th Ave N Horizon Way, Vedado Way, Via Miramar, Admiralty Point Beach Walk, 1977 Gulf Shore Blvd N pathway, Lowdermilk Park None Open
8th Ave N to 6th Ave N 7th Ave N, North Lake Drive, 6th Ave N 8th Ave N Stormwater Outfall Project
4th Ave N to Central Ave None 4th, 3rd, 2nd and 1st Ave N, Central Ave Stormwater Outfall Project
1st Ave S to 11th Ave S 1st through 11th Ave S, Broad Ave S with restrooms None Open
Pier area 13th Ave S with restrooms 12th Ave S Naples Pier rebuild
14th Ave S to 3590 Gordon Dr 14th through 18th Ave S, 21st Ave S, 1900 Gulf Shore Blvd S, 2100 Gordon Dr S, 32nd and 33rd Ave S, 3590 Gordon Dr None Open; 21st Ave S has future reconstruction planned

The real gap in the middle of town runs from 6th Avenue North down to 1st Avenue South. Five beach ends in a row are closed there. If your usual walk starts at 2nd Avenue North, the nearest open way in is 6th Avenue North on one side or 1st Avenue South on the other. The only restrooms listed on the table are at Broad Avenue South and 13th Avenue South, on either side of the closed pier entrance.

Many of the open ends south of Central look different from the ones you remember. They come from the city's separate restoration of 30 of its 40 beach access points, designed with less pavement and what the city calls a more natural "Old Florida" look. Some ends got fewer benches than they used to have, and some that had none now have one or more. Memorial bench plaques damaged by Hurricane Ian are being reinstalled as each beach end is rebuilt. The city isn't taking new bench donations or plaque requests right now.

The Week Ahead on the South End

The open south ends sit a short walk from Third Street South, which has a busy week coming. The street's 49th annual tree lighting is Monday, November 23, from 6 to 9 p.m. From Tuesday through Saturday of Thanksgiving week, there's live music from 5 to 8 p.m., snowfall at 7 p.m., and shops open until 7 p.m. Thanksgiving Day itself, Thursday, November 26, has no programming. Starting November 25, participating shops will have letters for the new North Pole Delivery District, a letter-to-Santa tradition that runs through December 23.

Thanksgiving week also falls during the sand crews' break from November 26 through November 29. For four days there will be no trucks on the sand at all. An after-dinner walk from 13th Avenue South or Broad Avenue South will have just the beach and the Gulf, with the pier still fenced off to the side.

What the Beach Looks Like by Early 2027

If the county's schedule holds, the sand work ends before the end of 2026 and the fenced work zones come down section by section. The outfall project's road and drainage work along Gulf Shore Boulevard North is expected to be substantially complete by year-end. The north pump station gets its electrical work through January and is commissioned in early 2027. Kiewit's estimate for final completion is May 2027. The project's end goal is a beach with none of the eight stormwater pipes still emptying onto it.

Until then, the city's status page is the place to look when a beach end opens back up, since the city says it updates that page with schedule changes and progress.

If you're weighing a home or condo near the Gulf Shore Boulevard beach ends and want to understand what this construction means for that stretch, Shane Wilson and our team can talk it through with you. Get in touch.

Let’s Find Your Dream Home

Decades of waterfront expertise, deep local roots, and a passion for the Florida lifestyle define every client experience. The Shane “Waterfront” Wilson combines extensive real estate knowledge with unmatched insight into the Florida Keys and Southwest Florida markets—helping buyers and sellers navigate every step with confidence and ease.